This was the week of the cill board - or should that be sill board? (Either is ok apparently!) Regardless of the spelling ours have been expertly made on site by the carpenter working on our project, Ben Hughes. Ben has used kiln dried oak planks which he has had to join together to cope with the depth of the cills in OLF. Apparently using wide planks is a bad idea as these inevitably warp over time. The oak planks firstly have a central groove routed out of their edge so that small wooden ovals (called biscuits) can be inserted into the groove at intervals to bridge the joint between the edges in what's known as a "biscuit joint". The edges are also glued and then clamped and left until the bond is set.
The planks are prepared, biscuits inserted and glued before being clamped together.
Ben has joined these planks with such skill that you literally can't see the join in many cases where the grain matches. Once the boards were ready, each one was cut to fit, every cill being a unique size, just to make it a bit more of a challenge for Ben! Once fitted a couple of coats of Danish oil really brought out the beauty of the oak grain.
The first of the 14 bespoke oak cill boards are in place.
We had hoped to have the large chimney stack rebuilt this week however a bit of a debate over the final choice of chimney pots has delayed this until week 18. Nevertheless there were other small finishing bits and pieces of brickwork and pointing to get on with.
The last remaining render was removed from the east gable above the roof of the lean-to. Like the rest of this gable some of the brickwork was in poor shape and there was also quite a bit of repointing to be done.
The repointing of the roof verges in lime mortar is complete and repairs are started on the remaining brickwork on the east gable.
Repointing of the bases of the brick walls was completed this week and, as everywhere else, this is a two stage process with the mortar roughly applied at first before being scratched back and consolidated when partially dried to give the final finish. The drill holes from an old chemical injected damp proof treatment (unnecessary and useless) will be filled with lime mortar and should disappear once limewashed next spring.
Repointing the bases of walls is complete with only some old drill holes to fill.
After 17 weeks, the end is in sight. Next week the chimneys should hopefully be rebuilt and repointed. Other than that a few bits of brickwork require repointing or replacement bricks, a few rows of tiles will be lifted and relaid to meet the guttering more effectively and the ridge tiling will be replaced. Once these jobs are complete, the scaffold can come down and we can see what this old house really looks like at last after almost 5 months of highly skilled and painstaking restoration work.
Inside OLF there are still cills to be made and fitted, reveals and soffits to be made good and all kinds of patches and larger areas replastered where plumbing and electrical work has been done and where dry linings were removed during the grouting of the stone wall. The plasterers are booked for the start of week 19 and all of this will be complete before Christmas!
It'll not be long before the scaffold comes down and we get a closer look at the "new" Old Lawns Farmhouse!